Contingency Study and Supply Reliability Score
A plant-level contingency screening in the spirit of a utility N-1 study: every credible failure, what it damages, what clears it, and what it costs each load.
1. What this check does
Starting from your one-line, RokBench generates the credible failure events of every item (from a catalog of failure mechanisms matched to the equipment kind, age, environment and condition), combines them with breaker failure, standby-source failure, common-mode events in a room or route, and with the operating states the plant can be in (normal, running on the alternate supply after a utility loss, or with one item out for maintenance). For each event it works out the physical damage, which protective device clears it (including non-selective ground-fault trips and delayed arcing faults), and how each load is restored: seamlessly, by automatic transfer, by manual switching, after repair or after replacement. Events are then weighted with survey failure rates to give each load its outages per year, hours per year and availability, and the plant a supply reliability score and a capital score.
2. Inputs used
- The one-line model: equipment, connections, normally open ties and transfer switches, critical loads.
- Optional asset data per item: kind, install year, environment, condition, assembly (lineup), route (duct bank or tray), room, damage-limiting features (arc-flash detection, segregation, insulated bus, draw-out), available fault current and instantaneous pickup, system grounding.
- Ratings used for failure rates and the capital index: transformer and UPS kVA, generator kW, cable length, breaker frame.
3. Formulas and assumptions
- 1 · EventA credible failure of one item, e.g. a loose bus joint on SWBD arcs
- 2 · DamageWhat is physically lost: the bus section, the whole lineup, or nothing
- 3 · ClearingWhich protective device opens: the main breaker upstream, or more if not selective
- 4 · RestorationHow each load comes back: E1 seamless … E5 after replacement
- 5 · Hoursf × d for every affected load, summed over all events
How often each event happens
The survey failure rate of the item (TM 5-698-5) times its age, condition and environment multiplier, split over the failure mechanisms that apply to it by likelihood weight (1, 3 or 9). Faults that can start as a ground fault are split 80 % ground / 20 % phase (g). Rare utility events use a fixed share of the utility rate instead.
An event is weighted by the share of the year the plant spends in the state it starts from; the normal state gets the rest of the year, so an event is not counted twice.
Per-demand probabilities: breaker 0.005, generator start 0.02 (0.005 common cause), transfer switch 0.01, tie close 0.01, battery 0.02 lead-acid / 0.005 lithium (a hidden open cell, charger or string breaker shows up when the input is lost; only loads that would otherwise have ridden through are counted).
Total cooling loss assumes redundant (N+1) room cooling, so it needs a common cause. It sends a double-conversion UPS to static bypass (no outage); only a rectifier-only system stops, for 2.4 h. A prolonged loss (an assumed 10 % of cooling failures) also overheats the static switch and any STS in the room: the load is off 4 h, or until moved to the maintenance bypass.
How long the load is off
The grade comes from the event itself: what it damages, which protective device clears it and which paths are left. Return to service with temporary measures: switchgear and bus 72 h, transformer 336 h, generator 168 h.
What each load gets
Sum over every event that affects the load (planned maintenance shutdowns are counted separately).
Equipment rates only; the utility rate is a project setting and is not scaled.
Symbols
| Frequency of event e | 1/yr | |
| Survey failure rate, repair time and return-to-service time of item i | 1/yr, h, h | |
| Age, condition and environment multiplier of item i (1 when not entered) | ||
| Likelihood weight of the failure mechanism (1 rare, 3 occasional, 9 frequent) | ||
| Ground or phase share of a fault (0.8 / 0.2) where both are modelled, else 1 | ||
| Share of the year spent in the operating state the event starts from | ||
| How long load L is off after event e, from its restoration grade | h | |
| Outage hours, interruptions and availability of load L | h/yr, 1/yr, — |
- Deterministic screening: each event is evaluated on its own against the model, with no probability in the judgement itself. The catalog of mechanisms and the clearing and damage rules are RokBench’s own and are kept on the server.
- Restoration grades: E1 seamless or momentary, E2 automatic transfer, E3 manual switching (1.5 h after isolating a fault; 1 h when a source is lost and only a tie or alternate source has to be closed), E4 after repair (survey repair time), E5 after an assembly-destroying failure (return-to-service time with temporary measures: switchgear and bus 72 h, transformer 336 h). An arcing fault that fast clearing or arc protection confines to one compartment is repaired, not replaced. A critical load passes the N-1 criterion when every single contingency is restored by E2 or better.
- Failure rates and repair times come from the US Army survey USACE TM 5-698-5 (public). Utility outage rates (default: a US-average feeder, 1.3 sustained outages a year of 2 h and 5 momentary; presets for storm-exposed overhead, urban network and dedicated feeders, or your own numbers, in the Project tab), per-demand failure probabilities (generator start, transfer, breaker), durations per grade and the age, condition and environment multipliers are RokBench assumptions and are listed with every result.
- Bands, not points (since 0.30.0): every rate-derived result is run three times with the equipment failure rates at half, once and twice the survey values, and shown as low–high. The structural findings (single points of failure, N-1 per critical load) use no rates and are shown first. A 0–10 score (2 × (nines − 1) of the worst critical load) is still computed but appears only on the Compare page and in what-if deltas as a comparison aid; there is no percentile against the template library and no capital-cost score on the public pages.
- Independent double failures are approximated for the highest-risk items; events that affect no load are kept out of the totals.
- UPS (since 0.31.0): rectifier, inverter, DC-link and battery failures transfer to the static bypass and do not interrupt the load; what drops it is the output section — static switch, output breaker, output wiring. An external maintenance bypass (a UPS setting, on by default, not drawn) is a manual path around the UPS: planned UPS maintenance needs no shutdown and an output-section fault is restored by manual transfer (E3) instead of repair. Room-wide events (fire, flood, cooling loss) are counted once for the room in the contributor and action lists. A total room cooling loss (0.005 per room per year since 0.34.0, assuming redundant cooling units, so only a common cause takes them all out) sends a double-conversion UPS to its static bypass, which keeps the load on; distribution equipment and batteries do not trip on room temperature. Only a rectifier-only (DC) system, with no bypass, loses its output until cooling is restored (2.4 h). A prolonged cooling loss, assumed to be 10 % of cooling failures (no public rate found), also overheats the static switch and any static transfer switch in the room: the load is off for an assumed 4 h, or until it is moved to the maintenance bypass.
- Batteries bridge momentary interruptions and transfer times only: a load behind a UPS rides through an ATS transfer to a generator, but with no generator the utility outage outlasts the battery and counts as an interruption. Continuity: a transfer counts as continuous supply when it completes within the load's ride-through time (default 0.02 s, set per load) or the load is battery-backed. Default transfer times: STS 0.004 s, ATS 1 s or 10 s with generator start, automatic tie 0.5 s. Interruptions beyond the tolerance and events ridden through are reported as separate counts; the score follows outage hours.
Worked examples
Three textbook arrangements from the template library, run through the same engine as the Workbench (engine 0.48.0, 2026, US-average utility). Each table lists the events that cost the marked critical load the most hours, with their frequency f, restoration grade, duration d and contribution f × d. Numbered circles on the drawing match the table rows. Open any of them from the Workbench template picker to see every case.
One utility feed, radial
Everything between the utility and the load is in series. Utility outages pass straight through, a switchboard bus fault means days to return it to service, and a flood or fire in the shared room takes the transformer and the panels at once.
| # | Equipment — event | State | λ item, /yr | f, /yr | Grade | d, h | f × d, h/yr |
|---|---|---|---|---|---|---|---|
| 1 | UTIL — Multi-day utility outage | normal | 1.30 | 0.039 | E4 | 72 | 2.81 |
| 2 | UTIL — Utility sustained outage | normal | 1.30 | 1.30 | E4 | 2.0 | 2.60 |
| 3 | Room ER-1 — Electrical room flooding | common mode | — | 0.0010 | E5 | 336 | 0.336 |
| 4 | Room ER-1 — Sprinkler discharge in the electrical room | common mode | — | 0.0010 | E5 | 336 | 0.336 |
| 5 | SWBD — Loose bus joint overheats and arcs | normal | 0.0095 | 0.0029 | E5 | 72 | 0.205 |
| 6 | SWBD — Bus joint bolts relaxed | normal | 0.0095 | 0.0029 | E5 | 72 | 0.205 |
| 7 | Room ER-1 — Electrical room fire | common mode | — | 0.00050 | E5 | 336 | 0.168 |
| 8 | SWBD — Arc flash while racking a breaker or bucket | normal | 0.0095 | 0.00095 | E5 | 72 | 0.068 |
| 81 other events | 0.288 | ||||||
| L-2: outage hours per year, HL = Σ f × d (rows are rounded) | 7.01 | ||||||
L-2: 7.4 interruptions a year; availability 99.920 % (3.1 nines).
Secondary selective (main-tie-main)
A utility or transformer loss is now restored by closing the normally open tie: about an hour of switching (E3) instead of waiting for the utility or replacing the transformer. The bus the load sits on, and the room it shares with its supply, stay in series.
| # | Equipment — event | State | λ item, /yr | f, /yr | Grade | d, h | f × d, h/yr |
|---|---|---|---|---|---|---|---|
| 1 | FDR-A — Utility sustained outage | normal | 1.30 | 1.25 | E3 | 1.0 | 1.25 |
| 2 | Room ER-A — Electrical room flooding | common mode | — | 0.0010 | E5 | 336 | 0.336 |
| 3 | Room ER-A — Sprinkler discharge in the electrical room | common mode | — | 0.0010 | E5 | 336 | 0.336 |
| 4 | BUS-A — Loose bus joint overheats and arcs | normal | 0.0095 | 0.0039 | E5 | 72 | 0.282 |
| 5 | BUS-A — Bus joint bolts relaxed | normal | 0.0095 | 0.0039 | E5 | 72 | 0.282 |
| 6 | Room ER-A — Electrical room fire | common mode | — | 0.00050 | E5 | 336 | 0.168 |
| 7 | FDR-A — Loss of one phase (single-phasing) | normal | 1.30 | 0.062 | E3 | 1.0 | 0.062 |
| 8 | FDR-A — Multi-day utility outage | normal | 1.30 | 0.037 | E3 | 1.0 | 0.037 |
| 140 other events | 0.330 | ||||||
| L-A: outage hours per year, HL = Σ f × d (rows are rounded) | 3.09 | ||||||
L-A: 7.2 interruptions a year; availability 99.965 % (3.5 nines).
Single UPS with battery and maintenance bypass
Short utility dips ride through on the battery and inverter or rectifier failures go to the static bypass, so they cost no hours. With no generator a utility outage outlasts the battery, and the output bus and the switchboard stay in series. A room cooling loss only sends the UPS to bypass, so it costs no hours either.
| # | Equipment — event | State | λ item, /yr | f, /yr | Grade | d, h | f × d, h/yr |
|---|---|---|---|---|---|---|---|
| 1 | UTIL — Multi-day utility outage | normal | 1.30 | 0.039 | E4 | 72 | 2.80 |
| 2 | UTIL — Utility sustained outage | normal | 1.30 | 1.30 | E4 | 2.0 | 2.59 |
| 3 | Room ER-1 — Electrical room flooding | common mode | — | 0.0010 | E5 | 336 | 0.336 |
| 4 | Room ER-1 — Sprinkler discharge in the electrical room | common mode | — | 0.0010 | E5 | 336 | 0.336 |
| 5 | UPS-BUS — Loose bus joint overheats and arcs | normal | 0.0095 | 0.0040 | E5 | 72 | 0.292 |
| 6 | UPS-BUS — Bus joint bolts relaxed | normal | 0.0095 | 0.0040 | E5 | 72 | 0.292 |
| 7 | SWBD — Loose bus joint overheats and arcs | normal | 0.0095 | 0.0028 | E5 | 72 | 0.204 |
| 8 | SWBD — Bus joint bolts relaxed | normal | 0.0095 | 0.0028 | E5 | 72 | 0.204 |
| 127 other events | 0.861 | ||||||
| L-1: outage hours per year, HL = Σ f × d (rows are rounded) | 7.92 | ||||||
L-1: 1.5 interruptions a year, 6 dips ridden through; availability 99.910 % (3.0 nines).
λ item is the survey rate of that piece of equipment with its multipliers; an event's f is its share of λ (split over the mechanisms that apply, and over phase and ground faults), or a per-room rate for fire, flood and cooling. Utility events use the utility rate of the project. The same model gives the same numbers in the Workbench.
4. What is NOT checked
- Load flow, voltage and short-circuit withstand under each contingency (use the Loading and Short-Circuit tools).
- Relay settings and coordination (time-current curves, ground-fault protection, zone-selective interlocking). The study uses instantaneous pickup thresholds only: a fault above the upstream breaker's instantaneous pickup trips it too unless that breaker has a short-time delay; ground faults are assumed to trip the nearest device selectively. Protective-device failures (relay, CT/VT, breaker failing to trip) are included.
- Human-factor and weather event frequencies specific to a site; the assumptions are generic.
- Planned maintenance is reported as a shutdown need, not counted in the outage hours.
5. Reference standards
Pointers only; consult the edition adopted by your authority having jurisdiction.
- IEEE Std 493 (Gold Book) — design of reliable industrial and commercial power systems (method; tables not reproduced)
- Published topology comparisons used as order-of-merit checks, not as inputs: Schneider Electric WP75 rev. 4 (UPS configurations); Callou, Maciel and Tutsch, Energies 2014 (CC BY) and InTech 2012 (CC BY); Shrestha et al., IEEE Access 2018 (AC vs 380 V DC, OSTI copy); Otani and Vedros, INL/PSAM16 2022 (substation bus schemes); Heising, IEEE Trans. IGA 1970 (radial vs selective); Sandia SAND2020-11209 (secondary networks). Summary in the repository notes docs/research/TOPOLOGY_LITERATURE.md
- USACE TM 5-698-5 — survey of reliability and availability information for power distribution, power generation and HVAC components
- NFPA 70B — electrical equipment maintenance
- IEEE Std 1584 and NFPA 70E — arcing-fault behavior (context for delayed clearing)
- NERC TPL-001 (transmission system planning performance) and utility N-1 contingency practice — the pattern this study follows at plant scale
- IEEE Std 3006.7 / 3006.8 — reliability of commercial and industrial power systems (indices: interruptions, hours, availability)
6. Validation cases
No worked example with a published answer is registered for this page yet. Have one we should add? Use the Feedback link. All cases: Validation.
7. Known issues and changes
See the Engineering Notes. Try the tool: Workbench (Contingency tab).